Initiative to remove discrepancies related to main road routes in Raipur Master Plan (Revised) 2031
Claims, objections and suggestions invited from common citizens, landowners and related stakeholders on the proposed amendment
Recommendation for re-inclusion of 11 routes, widening of 23 routes and reversal of alignment of 10 routes
The committee constituted under the chairmanship of the Director of Town and Country Planning examined more than 170 suggestions and applications.
Raipur, November 23, 2026/ Keeping in mind the planned development of Raipur city, future traffic needs and convenience of citizens, the state government has taken an important initiative towards necessary amendments in the road-related provisions of the Raipur Development Plan (Revised) 2031. Claims, objections and suggestions are being invited from common citizens, landowners and related stakeholders on the proposed amendments to remove the discrepancies related to the main roads under the Raipur Master Plan.
The Raipur Master Plan 2021 was originally published on April 7, 2008. After reviewing this master plan, the plan was republished on July 24, 2023. On March 15, 2024, the state government constituted an inquiry committee under the chairmanship of the Director of Town and Country Planning to examine the complaints and irregularities received in connection with the revised plan.
The committee received over 170 suggestions and applications regarding irregularities and discrepancies. The committee compared the original and reviewed development plans, examining these applications in light of site conditions, previously approved development permits, revenue records, current land use, existing routes, and future traffic needs. Following the investigation, the committee submitted its report to the state government.
Recommendation to include 11 routes again in the master plan
The Inquiry Committee found that 11 routes were deleted or altered under the Development Plan, which was reviewed in July 2023. Finding these routes essential for a smooth traffic system, the Committee recommended reincorporating them into the Master Plan.
Recommendation to restore the width of 23 routes as per the 2021 plan
The committee's review found that the proposed width of 23 roads had been reduced under the development plan reviewed in July 2023. To ensure a smoother traffic flow, the committee recommended restoring the width of these roads to the original 2021 plan.
Recommendation to reverse the alignment of 10 routes
The alignment of 10 routes was found to have been changed under the revised development plan in July 2023. The committee recommended restoring the alignments of these routes. This includes reverting the alignments of MR-33 and MR-40 to the original 2021 plan.
Initiative to resolve discrepancies regarding the names and width of major roads and intersections
In the Master Plan 2021, a table listing major roads and intersections in Raipur city included the names and widths of these roads. In the July 2023 review of the development plan, it was found that some names and many widths had been omitted from these tables. This has led to discrepancies in the development permit process. The committee has recommended restoring these tables.
Apart from this, objections have also been received on issues like incompatible land use, green areas, water bodies etc. other than the routes, regarding which separate action is underway.
Claims and objections invited under Section 23-A of the Chhattisgarh Town and Village Investment Act
Based on the recommendations of the committee related to roads, the proposal for modification in the Raipur Master Plan (Revised) is being invited for claims, objections and suggestions from the general public, landowners and related stakeholders within the prescribed process and period under Section 23-A of the Chhattisgarh Town and Country Planning Act, 1973. Its objective is to ensure public participation and transparency in the development plan.